| Assessment Year | 2016 |
|---|---|
| Principal Product | PVC based products |
| NAICS | 326121: Unlaminated Plastics Profile Shape Manufacturing |
| SIC | 3082: Unsupported Plastics Profile Shapes |
| Sales Range | $50 M to 100M |
| # of Employees | 239 |
| Plant Area |
184,540
ft2
|
| Annual Production | 4,500,000
lb
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,807,365 | 29,139,662 |
kWh
|
$0.062 |
| Electricity Demand | $469,709 | 57,387 |
kW-mo/yr
|
$8.18 |
| Electricity Fees | $10,805 | - |
|
- |
| Natural Gas | $26,625 | 3,301 |
MMBtu
|
$8.07 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $251,533 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $196,959 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,334 | $1,000 |
$4,352
70,194
kWh
|
$982
-
kW-mo/yr
|
- | |
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $43,060 | $25,900 |
$37,416
603,479
kWh
|
$5,644
-
kW-mo/yr
|
- | |
| 03 | 2.7261: Install timers and/or thermostats | $2,202 | $1,830 |
$1,249
20,153
kWh
|
- |
$952
-
MMBtu
|
|
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $66,277 | $63,000 |
$56,453
910,531
kWh
|
$9,824
-
kW-mo/yr
|
- | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $52,235 | $60,700 |
$45,388
732,062
kWh
|
$6,847
-
kW-mo/yr
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $38,176 | $61,332 |
$32,123
518,112
kWh
|
$6,053
-
kW-mo/yr
|
- | |
| 07 | 2.4226: Use / purchase optimum sized compressor | $41,911 | $70,000 |
$35,490
572,412
kWh
|
$6,421
-
kW-mo/yr
|
- | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,339 | $8,602 |
$1,374
22,163
kWh
|
$965
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $251,533 | $292,364 |
$213,845
3,449,106
kWh
|
$36,736
-
kW-mo/yr
|
$952
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $196,959 | $223,062 |
$167,083
2,694,881
kWh
|
$28,924
-
kW-mo/yr
|
$952
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs