| Assessment Year | 2014 |
|---|---|
| Principal Product | Extruded Tubing |
| NAICS | 333249: Other Industrial Machinery Manufacturing |
| SIC | 3559: Special Industry Machinery, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 65 |
| Plant Area |
60,000
ft2
|
| Annual Production | 622,479
lb
|
| Production Hrs. Annual | 4,080
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $145,843 | 2,082,400 |
kWh
|
$0.070 |
| Electricity Demand | $32,159 | 5,012 |
kW-mo/yr
|
$6.42 |
| Electricity Fees | $124,327 | - |
|
- |
| Natural Gas | $22,420 | 2,323 |
MMBtu
|
$9.65 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $42,191 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,723 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,081 | $40 |
$2,426
34,664
kWh
|
$655
-
kW-mo/yr
|
- | - | |
| 02 | 2.7261: Install timers and/or thermostats | $1,602 | $225 | - | - |
$1,602
-
MMBtu
|
- | |
| 03 | 2.7261: Install timers and/or thermostats | $2,644 | $900 | - | - |
$2,644
-
MMBtu
|
- | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,923 | $1,680 |
$1,803
25,763
kWh
|
$3,120
-
kW-mo/yr
|
- | - | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $1,017 | $500 |
$773
11,040
kWh
|
$244
-
kW-mo/yr
|
- | - | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,721 | $1,500 |
$2,077
29,676
kWh
|
$644
-
kW-mo/yr
|
- | - | |
| 07 | 2.7135: Install occupancy sensors | $5,736 | $8,213 |
$4,597
65,672
kWh
|
$1,002
-
kW-mo/yr
|
- | $137 | |
| 08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,950 | $11,700 |
$5,473
78,181
kWh
|
$1,477
-
kW-mo/yr
|
- | - | |
| 09 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,611 | $3,025 | - |
$1,611
-
kW-mo/yr
|
- | - | |
| 10 | 2.7135: Install occupancy sensors | $6,671 | $12,825 |
$4,601
65,729
kWh
|
$1,611
-
kW-mo/yr
|
- | $459 | |
| 11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $396 | $780 |
$186
2,652
kWh
|
$100
-
kW-mo/yr
|
- | $110 | |
| 12 | 2.4323: Use optimum size and capacity equipment | $2,820 | $6,500 |
$2,820
40,284
kWh
|
- | - | - | |
| 13 | 2.2437: Recover waste heat from equipment | $330 | $1,250 | - | - |
$330
-
MMBtu
|
- | |
| 14 | 2.4226: Use / purchase optimum sized compressor | $1,690 | $8,000 |
$1,330
19,006
kWh
|
$360
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $42,191 | $57,138 |
$26,086
372,667
kWh
|
$10,824
-
kW-mo/yr
|
$4,576
-
MMBtu
|
$706 | ||
| TOTAL IMPLEMENTED | $7,723 | $1,945 |
$2,612
37,316
kWh
|
$755
-
kW-mo/yr
|
$4,246
-
MMBtu
|
$110 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs