Assessment Year | 2014 |
---|---|
Principal Product | Fabricated Metal Products |
NAICS | 332313: Plate Work Manufacturing |
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $50 M to 100M |
# of Employees | 100 |
Plant Area |
102,599
ft2
|
Annual Production | 25,000
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $140,068 | 2,067,967 |
kWh
|
$0.068 |
Electricity Demand | $27,423 | 6,439 |
kW-mo/yr
|
$4.26 |
Electricity Fees | $18,308 | - |
|
- |
LPG | $101,217 | 5,603 |
MMBtu
|
$18.06 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $114,931 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,843 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $3,349 | - | - | - |
$3,349
-
MMBtu
|
- | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,947 | $35 |
$1,474
21,671
kWh
|
$473
-
kW-mo/yr
|
- | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $2,490 | $200 |
$2,222
32,671
kWh
|
$268
-
kW-mo/yr
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,076 | $1,000 |
$2,744
40,360
kWh
|
$332
-
kW-mo/yr
|
- | - | - | |
05 | 2.4323: Use optimum size and capacity equipment | $5,981 | $2,653 |
$5,981
87,966
kWh
|
- | - | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,997 | $4,187 |
$4,822
70,914
kWh
|
$175
-
kW-mo/yr
|
- | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,755 | $1,688 |
$9
137
kWh
|
$153
-
kW-mo/yr
|
- | - | $1,593 | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $11,133 | $15,100 |
$9,936
146,117
kWh
|
$1,197
-
kW-mo/yr
|
- | - | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,137 | $6,750 |
$2,549
37,481
kWh
|
$588
-
kW-mo/yr
|
- | - | - | |
10 | 2.1224: Replace boiler | $61,996 | $205,000 | - | - | - | $61,996 | - | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,070 | $75,880 |
$11,457
168,480
kWh
|
$1,380
-
kW-mo/yr
|
- | - | $2,233 | |
TOTAL RECOMMENDED | $114,931 | $312,493 |
$41,194
605,797
kWh
|
$4,566
-
kW-mo/yr
|
$3,349
-
MMBtu
|
$61,996 | $3,826 | ||
TOTAL IMPLEMENTED | $16,843 | $3,888 |
$12,421
182,668
kWh
|
$1,073
-
kW-mo/yr
|
$3,349
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs