Assessment Year | 2013 |
---|---|
Principal Product | Soup |
NAICS | 311422: Specialty Canning |
SIC | 2032: Canned Specialties |
Sales Range | $100 M to 500M |
# of Employees | 400 |
Plant Area |
450,000
ft2
|
Annual Production | 260,000,000
pieces
|
Production Hrs. Annual | 5,472
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,945,565 | 16,614,700 |
kWh
|
$0.12 |
Electricity Demand | $243,261 | 26,449 |
kW-mo/yr
|
$9.20 |
Natural Gas | $1,229,915 | 245,930 |
MMBtu
|
$5.00 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,237,977 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $99,048 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3416: Use combined cycle gas turbine generator sets with waste heat boilers connected to turbine exhaust | $990,391 | $2,480,000 |
$1,152,403
9,849,598
kWh
|
$198,720
-
kW-mo/yr
|
$(-306,559.0)
-
MMBtu
|
- | $(-54,173.0) | |
02 | 2.2442: Preheat combustion air with waste heat | $41,310 | $87,100 | - | - |
$41,310
-
MMBtu
|
- | - | |
03 | 2.7261: Install timers and/or thermostats | $992 | $225 |
$992
8,477
kWh
|
- | - | - | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $143,805 | $5,420 | - | - |
$143,805
-
MMBtu
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $29,839 | - |
$25,451
217,532
kWh
|
$4,388
-
kW-mo/yr
|
- | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,062 | $3,910 |
$4,241
36,247
kWh
|
$727
-
kW-mo/yr
|
- | - | $94 | |
07 | 2.7232: Replace existing hvac unit with high efficiency model | $4,733 | $11,400 |
$3,519
30,076
kWh
|
$1,214
-
kW-mo/yr
|
- | - | - | |
08 | 2.2135: Repair and eliminate steam leaks | $1,285 | $4,500 | - | - |
$1,285
-
MMBtu
|
- | - | |
09 | 2.3212: Optimize plant power factor | $20,522 | $42,000 | - | - | - | $20,522 | - | |
10 | 2.7442: Keep doors and windows shut when not on use | $38 | $110 |
$38
328
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $1,237,977 | $2,634,665 |
$1,186,644
10,142,258
kWh
|
$205,049
-
kW-mo/yr
|
$(-120,159.0)
-
MMBtu
|
$20,522 | $(-54,079.0) | ||
TOTAL IMPLEMENTED | $99,048 | $137,845 |
$30,722
262,584
kWh
|
$5,115
-
kW-mo/yr
|
$42,595
-
MMBtu
|
$20,522 | $94 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs