ITAC Assessment: LE0356
ITAC logo
ITAC Assessment: LE0356
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Metal strip and foil
NAICS 331491: Nonferrous Metal (except Copper and Aluminum) Rolling, Drawing, and Extruding
SIC 3356: Rolling, Drawing, and Extruding of Nonferrous Metals, Except Copper and Aluminum
Sales Range $10
M
to 50
M
# of Employees 64
Plant Area 90,000
ft2
Annual Production 589,500
lb
Production Hrs. Annual 6,864
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $145,830 3,064,500
kWh
Electricity Demand $40,821 9,249
kW-mo/yr
Electricity Fees $121,539 -
Natural Gas $103,026 13,346
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $49,746 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $25,165

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,905 $5,175 - - - $2,905
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,126 $3,215 - - - $2,126
03 2.7491: Insulate glazing, walls, ceilings, and roofs $10,894 $51,200 - - $10,894
-
MMBtu
-
04 2.7444: Close holes and openings in building such as broken windows $146 $338 - - $146
-
MMBtu
-
05 2.1133: Adjust burners for efficient operation $756 - - - $756
-
MMBtu
-
06 2.4231: Reduce the pressure of compressed air to the minimum required $1,451 $520 $1,186
24,707
kWh
$265
-
kW-mo/yr
- -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,343 $1,000 $1,193
24,862
kWh
$150
-
kW-mo/yr
- -
08 2.4221: Install compressor air intakes in coolest locations $2,139 $1,500 $1,901
39,595
kWh
$238
-
kW-mo/yr
- -
09 2.2437: Recover waste heat from equipment $3,341 - - - $3,341
-
MMBtu
-
10 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,399 $3,700 $3,020
62,907
kWh
$379
-
kW-mo/yr
- -
11 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $8,608 $25,060 $7,642
159,204
kWh
$966
-
kW-mo/yr
- -
12 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $12,638 $1,086 $2,887
60,150
kWh
$9,751
-
kW-mo/yr
- -
TOTAL RECOMMENDED $49,746 $92,794 $17,829
371,425
kWh
$11,749
-
kW-mo/yr
$15,137
-
MMBtu
$5,031
TOTAL IMPLEMENTED $25,165 $13,176 $5,907
123,057
kWh
$10,130
-
kW-mo/yr
$4,097
-
MMBtu
$5,031
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs