Assessment Year | 2012 |
---|---|
Principal Product | Near net shape forgings and butt welded pipe fittings |
NAICS | 332996: Fabricated Pipe and Pipe Fitting Manufacturing |
SIC | 3494: Valves and Pipe Fittings, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 65 |
Plant Area |
225,000
ft2
|
Annual Production | 17,906
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $916,536 | 7,325,203 |
kWh
|
$0.13 |
Electricity Demand | $150,774 | 25,241 |
kW-mo/yr
|
$5.97 |
Natural Gas | $1,426,716 | 170,745 |
MMBtu
|
$8.36 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,308,001 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3322: Use existing dam to generate electricity | $1,144,296 | $10,386,800 | - | - | $1,144,296 | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $67,090 | $3,825 |
$9,999
79,694
kWh
|
$57,091
-
kW-mo/yr
|
- | - | - | |
03 | 2.4112: Install soft-start to eliminate nuisance trips | $19,961 | $32,500 | - |
$19,961
-
kW-mo/yr
|
- | - | - | |
04 | 2.6231: Utilize controls to operate equipment only when needed | $15,946 | $9,800 |
$15,946
127,566
kWh
|
- | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,640 | $1,000 |
$10,183
81,464
kWh
|
$1,457
-
kW-mo/yr
|
- | - | - | |
06 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $7,534 | $3,000 | - |
$7,534
-
kW-mo/yr
|
- | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $41,018 | $44,640 |
$35,535
284,280
kWh
|
$5,086
-
kW-mo/yr
|
- | - | $397 | |
08 | 2.7261: Install timers and/or thermostats | $516 | $125 | - | - | - |
$516
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $1,308,001 | $10,481,690 |
$71,663
573,004
kWh
|
$91,129
-
kW-mo/yr
|
$1,144,296 |
$516
-
MMBtu
|
$397 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs