| Assessment Year | 2000 |
|---|---|
| Principal Product | Steel processing |
| NAICS |
n/a
|
| SIC | 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills |
| Sales Range | $10 M to 50M |
| # of Employees | 80 |
| Plant Area |
296,050
ft2
|
| Annual Production | 850,000
ton
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Demand | $82,510 | 10,285 |
kW-mo/yr
|
$8.02 |
| Electricity Fees | $7,215 | - |
|
- |
| Natural Gas | $512,682 | 149,269 |
MMBtu
|
$3.43 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $385,335 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $187,954 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7135: Install occupancy sensors | $717 | $3,440 |
$717
24,326
kWh
|
- | - | - | - | - | |
| 02 | 2.2693: Use waste heat steam for absorption refrigeration | $15,476 | $30,000 |
$8,722
316,237
kWh
|
$6,754
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.1241: Reduce excessive boiler blowdown | $2,065 | $4,430 | - | - |
$2,065
-
MMBtu
|
- | - | - | |
| 04 | 3.3133: Use other waste concentration methods | $147,018 | $250,000 | - | - | - | - |
$147,018
-
gal
|
- | |
| 05 | 3.4111: Use closed cycle process to minimize waste water production | $32,105 | $3,600 | - | - | - |
$32,105
-
Tgal
|
- | - | |
| 06 | 4.111: Add equipment/ operators to reduce production bottleneck | $187,954 | $165,000 | - | - | - | - | - | $187,954 | |
| TOTAL RECOMMENDED | $385,335 | $456,470 |
$9,439
340,563
kWh
|
$6,754
-
kW-mo/yr
|
$2,065
-
MMBtu
|
$32,105
-
Tgal
|
$147,018
-
gal
|
$187,954 | ||
| TOTAL IMPLEMENTED | $187,954 | $165,000 | - | - | - | - | - | $187,954 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs