Assessment Year | 2010 |
---|---|
Principal Product | fluid milk |
NAICS | 311511: Fluid Milk Manufacturing |
SIC | 2026: Fluid Milk |
Sales Range | $1 M to 5M |
# of Employees | 252 |
Plant Area |
74,000
ft2
|
Annual Production | 62,500
Tgal
|
Production Hrs. Annual | 5,616
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $532,726 | 8,462,709 |
kWh
|
$0.063 |
Electricity Demand | $159,296 | 22,856 |
kW-mo/yr
|
$6.97 |
Natural Gas | $452,690 | 49,648 |
MMBtu
|
$9.12 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $305,297 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $88,267 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4226: Use / purchase optimum sized compressor | $189,768 | $90,000 |
$149,907
2,379,476
kWh
|
$39,861
-
kW-mo/yr
|
- | - | |
02 | 2.2511: Insulate bare equipment | $23,403 | $5,772 | - | - |
$23,403
-
MMBtu
|
- | |
03 | 2.7261: Install timers and/or thermostats | $21,770 | $250 |
$10,453
165,927
kWh
|
- |
$11,317
-
MMBtu
|
- | |
04 | 2.4226: Use / purchase optimum sized compressor | $16,145 | $20,000 |
$12,751
202,393
kWh
|
$3,394
-
kW-mo/yr
|
- | - | |
05 | 2.2442: Preheat combustion air with waste heat | $11,117 | $30,000 | - | - |
$11,117
-
MMBtu
|
- | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $6,925 | - |
$5,687
90,276
kWh
|
$1,238
-
kW-mo/yr
|
- | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,657 | $1,000 |
$5,259
83,478
kWh
|
$1,398
-
kW-mo/yr
|
- | - | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,494 | $40 |
$5,494
87,208
kWh
|
- | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $24,018 | $2,431 |
$17,331
275,089
kWh
|
$4,609
-
kW-mo/yr
|
- | $2,078 | |
TOTAL RECOMMENDED | $305,297 | $149,493 |
$206,882
3,283,847
kWh
|
$50,500
-
kW-mo/yr
|
$45,837
-
MMBtu
|
$2,078 | ||
TOTAL IMPLEMENTED | $88,267 | $9,493 |
$44,224
701,978
kWh
|
$7,245
-
kW-mo/yr
|
$34,720
-
MMBtu
|
$2,078 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs