ITAC Assessment: AS0365
ITAC logo
ITAC Assessment: AS0365
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Wood Fuel Pellets
NAICS 321999: All Other Miscellaneous Wood Product Manufacturing
SIC 2499: Wood Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 32
Plant Area 958,320
ft2
Annual Production 35,000
ton
Production Hrs. Annual 7,704
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $243,095 4,274,000
kWh
Electricity Demand $14,581 8,944
kW-mo/yr
Electricity Fees $16,610 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $100,160 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,682

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
01 2.4133: Use most efficient type of electric motors $790 $1,643 $680
14,903
kWh
$110
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $290 $1,535 $176
3,866
kWh
$95
-
kW-mo/yr
- $19
03 2.7135: Install occupancy sensors $140 $450 $140
3,074
kWh
- - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,328 $60 $5,783
126,826
kWh
$1,545
-
kW-mo/yr
- -
05 2.4231: Reduce the pressure of compressed air to the minimum required $183 $30 $144
3,159
kWh
$39
-
kW-mo/yr
- -
06 2.7232: Replace existing hvac unit with high efficiency model $274 $350 $167
3,657
kWh
$107
-
kW-mo/yr
- -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $88,723 $78,120 $78,541
1,740,885
kWh
$10,182
-
kW-mo/yr
- -
08 3.5311: Recover and reuse waste material $2,432 $1,059 n/a - - $2,432
-
lb
-
TOTAL RECOMMENDED $100,160 $83,247 $85,631
1,896,370
kWh
$12,078
-
kW-mo/yr
$2,432
-
lb
$19
TOTAL IMPLEMENTED $8,682 $3,588 $6,806
149,252
kWh
$1,857
-
kW-mo/yr
- $19
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs