| Assessment Year | 2010 |
|---|---|
| Principal Product | metering motors |
| NAICS | 333911: Pump and Pumping Equipment Manufacturing |
| SIC | 3561: Pumps and Pumping Equipment |
| Sales Range | $100 M to 500M |
| # of Employees | 212 |
| Plant Area |
100,000
ft2
|
| Annual Production | 21,000
units
|
| Production Hrs. Annual | 4,680
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $183,718 | 2,641,958 |
kWh
|
$0.070 |
| Electricity Demand | $98,032 | 6,937 |
kW-mo/yr
|
$14.13 |
| Natural Gas | $23,662 | 1,112 |
MMBtu
|
$21.28 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $52,091 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $15,904 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,029 | $785 |
$5,946
84,946
kWh
|
$3,083
-
kW-mo/yr
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,875 | $1,760 |
$4,530
64,720
kWh
|
$2,345
-
kW-mo/yr
|
- | - | |
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $4,903 | $3,000 | - |
$4,903
-
kW-mo/yr
|
- | - | |
| 04 | 2.7232: Replace existing hvac unit with high efficiency model | $4,627 | $66,360 |
$2,057
29,340
kWh
|
$1,151
-
kW-mo/yr
|
$1,419
-
MMBtu
|
- | |
| 05 | 2.7261: Install timers and/or thermostats | $2,326 | $450 |
$2,326
33,230
kWh
|
- | - | - | |
| 06 | 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle | $2,367 | $4,500 | - | - |
$2,367
-
MMBtu
|
- | |
| 07 | 2.2437: Recover waste heat from equipment | $2,239 | $1,000 |
$2,239
31,986
kWh
|
- | - | - | |
| 08 | 2.4221: Install compressor air intakes in coolest locations | $935 | $800 |
$652
9,319
kWh
|
$283
-
kW-mo/yr
|
- | - | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $17,807 | $55,184 |
$11,409
162,984
kWh
|
$5,786
-
kW-mo/yr
|
- | $612 | |
| 10 | 2.7135: Install occupancy sensors | $983 | $450 |
$983
14,040
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $52,091 | $134,289 |
$30,142
430,565
kWh
|
$17,551
-
kW-mo/yr
|
$3,786
-
MMBtu
|
$612 | ||
| TOTAL IMPLEMENTED | $15,904 | $2,545 |
$10,476
149,666
kWh
|
$5,428
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs