ITAC Assessment: LE0292
ITAC logo
ITAC Assessment: LE0292
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product fluorescent and HID light fixtures
NAICS 335122: Commercial, Industrial, and Institutional Electric Lighting Fixture Manufacturing
SIC 3645: Residential Electric Lighting Fixtures
Sales Range $50
M
to 100
M
# of Employees 250
Plant Area 285,000
ft2
Annual Production 1,500,000
units
Production Hrs. Annual 4,160
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $213,736 3,031,924
kWh
Electricity Demand $98,205 7,184
kW-mo/yr
Natural Gas $207,447 8,736
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $65,573 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $47,496

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $29,667 $27,000 $10,310
147,274
kWh
$19,357
-
kW-mo/yr
-
02 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle $11,701 $2,700 - - $11,701
-
MMBtu
03 2.7261: Install timers and/or thermostats $5,415 $180 - - $5,415
-
MMBtu
04 2.3131: Reschedule plant operations or reduce load to avoid peaks $4,921 $3,000 - $4,921
-
kW-mo/yr
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,424 $1,840 $2,825
40,425
kWh
$1,599
-
kW-mo/yr
-
06 2.4231: Reduce the pressure of compressed air to the minimum required $3,459 $200 $2,160
30,996
kWh
$1,299
-
kW-mo/yr
-
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,073 $3,000 $1,610
23,087
kWh
$1,463
-
kW-mo/yr
-
08 2.4221: Install compressor air intakes in coolest locations $1,952 $1,000 $1,173
16,752
kWh
$779
-
kW-mo/yr
-
09 2.7135: Install occupancy sensors $961 $420 $961
13,726
kWh
- -
TOTAL RECOMMENDED $65,573 $39,340 $19,039
272,260
kWh
$29,418
-
kW-mo/yr
$17,116
-
MMBtu
TOTAL IMPLEMENTED $47,496 $33,800 $15,041
215,083
kWh
$27,040
-
kW-mo/yr
$5,415
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs