Assessment Year | 2009 |
---|---|
Principal Product | closures cores and containers |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 215 |
Plant Area |
250,000
ft2
|
Annual Production | 100,000,000
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,358,228 | 18,092,630 |
kWh
|
$0.075 |
Electricity Demand | $246,734 | 37,030 |
kW-mo/yr
|
$6.66 |
Natural Gas | $24,993 | 19,814 |
MMBtu
|
$1.26 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $566,268 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,058 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4226: Use / purchase optimum sized compressor | $184,606 | $250,000 |
$137,606
1,834,746
kWh
|
$47,000
-
kW-mo/yr
|
- | |
02 | 2.7261: Install timers and/or thermostats | $220,823 | $50,000 |
$220,823
2,010,978
kWh
|
- | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $79,515 | $8,000 |
$67,807
904,090
kWh
|
$11,708
-
kW-mo/yr
|
- | |
04 | 2.7261: Install timers and/or thermostats | $36,003 | $650 |
$32,760
447,573
kWh
|
- |
$3,243
-
MMBtu
|
|
05 | 2.4226: Use / purchase optimum sized compressor | $19,644 | $17,000 |
$19,644
261,925
kWh
|
- | - | |
06 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $13,621 | $7,167 |
$11,636
155,148
kWh
|
$1,985
-
kW-mo/yr
|
- | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,058 | $1,840 |
$3,465
46,217
kWh
|
$593
-
kW-mo/yr
|
- | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,998 | $27,281 |
$6,819
92,190
kWh
|
$1,179
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $566,268 | $361,938 |
$500,560
5,752,867
kWh
|
$62,465
-
kW-mo/yr
|
$3,243
-
MMBtu
|
||
TOTAL IMPLEMENTED | $4,058 | $1,840 |
$3,465
46,217
kWh
|
$593
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs