Assessment Year | 2008 |
---|---|
Principal Product | rolled and coated aluminum |
NAICS | 331315: Aluminum Sheet, Plate, and Foil Manufacturing |
SIC | 3353: Aluminum Sheet, Plate, and Foil |
Sales Range | $10 M to 50M |
# of Employees | 154 |
Plant Area |
250,000
ft2
|
Annual Production | 20,800,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $540,554 | 11,567,403 |
kWh
|
$0.047 |
Electricity Demand | $262,201 | 36,184 |
kW-mo/yr
|
$7.25 |
Natural Gas | $928,287 | 80,380 |
MMBtu
|
$11.55 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $248,900 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,361 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $130,841 | $80,000 |
$95,490
2,031,706
kWh
|
$35,351
-
kW-mo/yr
|
- | - | |
02 | 2.4226: Use / purchase optimum sized compressor | $53,138 | $6,600 |
$40,610
864,037
kWh
|
$12,528
-
kW-mo/yr
|
- | - | |
03 | 2.7262: Separate controls of air handlers from ac/ heating systems | $18,111 | $40,000 | - | - |
$18,111
-
MMBtu
|
- | |
04 | 2.7262: Separate controls of air handlers from ac/ heating systems | $17,652 | $6,200 |
$1,174
24,976
kWh
|
$181
-
kW-mo/yr
|
$16,297
-
MMBtu
|
- | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,361 | $272 |
$3,331
70,882
kWh
|
$1,030
-
kW-mo/yr
|
- | - | |
06 | 2.7135: Install occupancy sensors | $2,647 | $480 |
$2,647
56,311
kWh
|
- | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $22,150 | $92,543 |
$14,458
307,617
kWh
|
$5,285
-
kW-mo/yr
|
- | $2,407 | |
TOTAL RECOMMENDED | $248,900 | $226,095 |
$157,710
3,355,529
kWh
|
$54,375
-
kW-mo/yr
|
$34,408
-
MMBtu
|
$2,407 | ||
TOTAL IMPLEMENTED | $4,361 | $272 |
$3,331
70,882
kWh
|
$1,030
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs