ITAC Assessment: LE0269
ITAC logo
ITAC Assessment: LE0269
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product flexible packaging
NAICS 323111: Commercial Printing (except Screen and Books)
SIC 2759: Commercial Printing, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 121
Plant Area 65,000
ft2
Annual Production 500,000,000
units
Production Hrs. Annual 8,736
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $264,450 4,946,939
kWh
Electricity Demand $114,586 8,072
kW-mo/yr
Natural Gas $239,502 25,873
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $276,338 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $217,332

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Increase in Production Savings
01 2.1336: Install equipment to utilize waste fuel $112,626 $500,000 $11,744
221,580
kWh
$5,085
-
kW-mo/yr
$95,797
-
MMBtu
- -
02 4.652: Replace existing equipment with more suitable substitutes $77,672 $600,000 $28,857
544,481
kWh
$9,968
-
kW-mo/yr
- $10,000 $28,847
03 2.7447: Install vinyl strip / high speed / air curtain doors $27,087 $9,000 - - $27,087
-
MMBtu
- -
04 2.7261: Install timers and/or thermostats $14,712 $250 $10,591
199,824
kWh
- $4,121
-
MMBtu
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,284 $3,500 $8,284
156,303
kWh
- - - -
06 2.7135: Install occupancy sensors $6,589 $720 $6,589
124,331
kWh
- - - -
07 2.3131: Reschedule plant operations or reduce load to avoid peaks $5,734 $3,000 - $5,734
-
kW-mo/yr
- - -
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $4,038 $900 $2,866
54,082
kWh
$1,172
-
kW-mo/yr
- - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $19,596 $36,313 $14,324
270,266
kWh
$5,272
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $276,338 $1,153,683 $83,255
1,570,867
kWh
$27,231
-
kW-mo/yr
$127,005
-
MMBtu
$10,000 $28,847
TOTAL IMPLEMENTED $217,332 $1,104,650 $62,342
1,176,270
kWh
$16,225
-
kW-mo/yr
$99,918
-
MMBtu
$10,000 $28,847
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs