ITAC Assessment: LE0262
ITAC logo
ITAC Assessment: LE0262
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Progressive adult beverages
NAICS 312120: Breweries
SIC 2099: Food Preparations, Not Elsewhere Classified
Sales Range greater than $500
M
# of Employees 250
Plant Area 881,000
ft2
Annual Production 117,000,000
lb
Production Hrs. Annual 7,448
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,354,751 24,955,000
kWh
Electricity Demand $269,064 42,408
kW-mo/yr
Natural Gas $1,736,736 155,578
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,097,774 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.9114: Use solar heat to make electricty $204,947 $1,684,540 $204,947
3,701,184
kWh
- -
02 2.2113: Repair or replace steam traps $427,857 $118,000 - - $427,857
-
MMBtu
03 2.2628: Utilize a less expensive cooling method $173,079 $300,000 $145,547
2,695,317
kWh
$27,532
-
kW-mo/yr
-
04 2.2449: Recover heat from exhausted steam, hot air or hot water $118,106 $75,000 - - $118,106
-
MMBtu
05 2.4226: Use / purchase optimum sized compressor $40,484 $1,000 $36,984
684,924
kWh
$3,500
-
kW-mo/yr
-
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $36,726 $36,000 $30,884
571,918
kWh
$5,842
-
kW-mo/yr
-
07 2.2113: Repair or replace steam traps $16,954 $4,200 - - $16,954
-
MMBtu
08 2.6218: Turn off equipment when not in use $13,938 $500 - - $13,938
-
MMBtu
09 2.7261: Install timers and/or thermostats $9,758 $960 $9,758
180,706
kWh
- -
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,332 $2,000 $8,696
161,037
kWh
$1,636
-
kW-mo/yr
-
11 2.3131: Reschedule plant operations or reduce load to avoid peaks $8,066 $4,000 - $8,066
-
kW-mo/yr
-
12 2.4231: Reduce the pressure of compressed air to the minimum required $5,980 $1,400 $4,843
89,689
kWh
$1,137
-
kW-mo/yr
-
13 2.4111: Utilize energy-efficient belts and other improved mechanisms $4,168 $1,000 $3,465
64,174
kWh
$703
-
kW-mo/yr
-
14 2.2136: Install / repair insulation on steam lines $1,804 $535 - - $1,804
-
MMBtu
15 2.7135: Install occupancy sensors $25,575 $11,250 $25,575
473,621
kWh
- -
TOTAL RECOMMENDED $1,097,774 $2,240,385 $470,699
8,622,570
kWh
$48,416
-
kW-mo/yr
$578,659
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs