Assessment Year | 2007 |
---|---|
Principal Product | Progressive adult beverages |
NAICS | 312120: Breweries |
SIC | 2099: Food Preparations, Not Elsewhere Classified |
Sales Range | greater than $500 M |
# of Employees | 250 |
Plant Area |
881,000
ft2
|
Annual Production | 117,000,000
lb
|
Production Hrs. Annual | 7,448
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,354,751 | 24,955,000 |
kWh
|
$0.054 |
Electricity Demand | $269,064 | 42,408 |
kW-mo/yr
|
$6.34 |
Natural Gas | $1,736,736 | 155,578 |
MMBtu
|
$11.16 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,097,774 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $204,947 | $1,684,540 |
$204,947
3,701,184
kWh
|
- | - | |
02 | 2.2113: Repair or replace steam traps | $427,857 | $118,000 | - | - |
$427,857
-
MMBtu
|
|
03 | 2.2628: Utilize a less expensive cooling method | $173,079 | $300,000 |
$145,547
2,695,317
kWh
|
$27,532
-
kW-mo/yr
|
- | |
04 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $118,106 | $75,000 | - | - |
$118,106
-
MMBtu
|
|
05 | 2.4226: Use / purchase optimum sized compressor | $40,484 | $1,000 |
$36,984
684,924
kWh
|
$3,500
-
kW-mo/yr
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $36,726 | $36,000 |
$30,884
571,918
kWh
|
$5,842
-
kW-mo/yr
|
- | |
07 | 2.2113: Repair or replace steam traps | $16,954 | $4,200 | - | - |
$16,954
-
MMBtu
|
|
08 | 2.6218: Turn off equipment when not in use | $13,938 | $500 | - | - |
$13,938
-
MMBtu
|
|
09 | 2.7261: Install timers and/or thermostats | $9,758 | $960 |
$9,758
180,706
kWh
|
- | - | |
10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,332 | $2,000 |
$8,696
161,037
kWh
|
$1,636
-
kW-mo/yr
|
- | |
11 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $8,066 | $4,000 | - |
$8,066
-
kW-mo/yr
|
- | |
12 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,980 | $1,400 |
$4,843
89,689
kWh
|
$1,137
-
kW-mo/yr
|
- | |
13 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,168 | $1,000 |
$3,465
64,174
kWh
|
$703
-
kW-mo/yr
|
- | |
14 | 2.2136: Install / repair insulation on steam lines | $1,804 | $535 | - | - |
$1,804
-
MMBtu
|
|
15 | 2.7135: Install occupancy sensors | $25,575 | $11,250 |
$25,575
473,621
kWh
|
- | - | |
TOTAL RECOMMENDED | $1,097,774 | $2,240,385 |
$470,699
8,622,570
kWh
|
$48,416
-
kW-mo/yr
|
$578,659
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs