Assessment Year | 2006 |
---|---|
Principal Product | UHT milk |
NAICS | 311511: Fluid Milk Manufacturing |
SIC | 2026: Fluid Milk |
Sales Range | $50 M to 100M |
# of Employees | 170 |
Plant Area |
80,000
ft2
|
Annual Production | 30,000
Tgal
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $744,517 | 11,575,000 |
kWh
|
$0.064 |
Electricity Demand | $132,747 | 22,051 |
kW-mo/yr
|
$6.02 |
Natural Gas | $1,201,835 | 117,849 |
MMBtu
|
$10.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $494,199 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $25,762 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8113: Purchase gas directly from a contract gas supplier | $318,192 | $1,250 | - | - |
$318,192
-
MMBtu
|
- | - | |
02 | 2.2113: Repair or replace steam traps | $47,703 | $5,000 | - | - |
$47,703
-
MMBtu
|
- | - | |
03 | 3.5132: Reuse rich white water in other applications | $43,680 | $5,000 | - | - | - |
$19,656
-
Tgal
|
$24,024
-
Tgal
|
|
04 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $41,698 | $30,000 | - | - |
$41,698
-
MMBtu
|
- | - | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $10,138 | $2,500 | - | - |
$10,138
-
MMBtu
|
- | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $9,828 | $8,700 |
$7,809
122,022
kWh
|
$2,019
-
kW-mo/yr
|
- | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,030 | $2,000 |
$6,225
97,271
kWh
|
$805
-
kW-mo/yr
|
- | - | - | |
08 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $6,646 | $2,500 | - |
$6,646
-
kW-mo/yr
|
- | - | - | |
09 | 2.4221: Install compressor air intakes in coolest locations | $5,796 | $3,000 |
$4,886
76,324
kWh
|
$910
-
kW-mo/yr
|
- | - | - | |
10 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,488 | $1,000 |
$3,001
46,923
kWh
|
$487
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $494,199 | $60,950 |
$21,921
342,540
kWh
|
$10,867
-
kW-mo/yr
|
$417,731
-
MMBtu
|
$19,656
-
Tgal
|
$24,024
-
Tgal
|
||
TOTAL IMPLEMENTED | $25,762 | $14,200 |
$12,695
198,346
kWh
|
$2,929
-
kW-mo/yr
|
$10,138
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs