Assessment Year | 2005 |
---|---|
Principal Product | Metal cutting saw blades |
NAICS | 332216: Saw Blade and Handtool Manufacturing |
SIC | 2425: |
Sales Range | $1 M to 5M |
# of Employees | 26 |
Plant Area |
129,213
ft2
|
Annual Production | 8,722
ton
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $120,292 | 1,392,000 |
kWh
|
$0.086 |
Electricity Demand | $23,364 | 3,881 |
kW-mo/yr
|
$6.02 |
Natural Gas | $231,376 | 22,089 |
MMBtu
|
$10.47 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $76,406 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $31,769 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 4.445: Install equipment to move product | $28,200 | $2,000 | - | - | - | $28,200 | |
02 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $17,500 | $50,000 | - | - |
$17,500
-
MMBtu
|
- | |
03 | 2.7261: Install timers and/or thermostats | $11,161 | $2,800 | - | - |
$11,161
-
MMBtu
|
- | |
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,707 | $200 | - |
$5,707
-
kW-mo/yr
|
- | - | |
05 | 2.4226: Use / purchase optimum sized compressor | $4,158 | $800 |
$3,436
39,948
kWh
|
$722
-
kW-mo/yr
|
- | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,558 | $100 |
$2,114
24,584
kWh
|
$444
-
kW-mo/yr
|
- | - | |
07 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $1,914 | $2,500 | - | - |
$1,914
-
MMBtu
|
- | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,118 | $350 |
$924
10,742
kWh
|
$194
-
kW-mo/yr
|
- | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,090 | $35,595 |
$3,151
36,640
kWh
|
$939
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $76,406 | $94,345 |
$9,625
111,914
kWh
|
$8,006
-
kW-mo/yr
|
$30,575
-
MMBtu
|
$28,200 | ||
TOTAL IMPLEMENTED | $31,769 | $88,395 |
$5,265
61,224
kWh
|
$7,090
-
kW-mo/yr
|
$19,414
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs