| Assessment Year | 2017 |
|---|---|
| Principal Product | Printed and Die-Cut Components |
| NAICS | 323111: Commercial Printing (except Screen and Books) |
| SIC | 2759: Commercial Printing, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 95 |
| Plant Area |
100,000
ft2
|
| Annual Production | 6,190,500
units
|
| Production Hrs. Annual | 5,900
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $156,248 | 1,757,600 |
kWh
|
$0.089 | |
| Electricity Demand | $52,934 | 5,292 |
kW-mo/yr
|
$10.00 | |
| Electricity Fees | $40,979 | - |
|
- | |
| Natural Gas | $7,588 | 6,139 |
MMBtu
|
$1.24 | |
| Waste Disposal Costs | |||||
| Water Usage | $5,274 | 615 |
Tgal
|
$8.57 | |
| TOTAL YEARLY COSTS | $263,023 | ||||
| RECOMMENDED SAVINGS* | $48,708 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $47,992 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,407 | $2,838 |
$1,247
14,016
kWh
|
$160
-
kW-mo/yr
|
|
| 02 | 2.7132: Install timers on light switches in little used areas | $716 | $675 |
$716
8,049
kWh
|
- | |
| 03 | 2.4224: Upgrade controls on compressors | $27,764 | $4,325 |
$23,473
263,737
kWh
|
$4,291
-
kW-mo/yr
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $18,821 | $140 |
$15,320
172,139
kWh
|
$3,501
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $48,708 | $7,978 |
$40,756
457,941
kWh
|
$7,952
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $47,992 | $7,303 |
$40,040
449,892
kWh
|
$7,952
-
kW-mo/yr
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs