Assessment Year | 2003 |
---|---|
Principal Product | Seals |
NAICS | 332912: Fluid Power Valve and Hose Fitting Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 187 |
Plant Area |
100,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 5,460
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $198,314 | 2,717,800 |
kWh
|
$0.073 |
Electricity Demand | $123,151 | 10,237 |
kW-mo/yr
|
$12.03 |
Natural Gas | $19,500 | 1,928 |
MMBtu
|
$10.11 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $56,594 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,136 | $150 |
$3,061
40,658
kWh
|
$1,075
-
kW-mo/yr
|
- | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $11,194 | $4,000 |
$7,922
105,206
kWh
|
$3,272
-
kW-mo/yr
|
- | - | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,205 | - |
$835
11,083
kWh
|
$370
-
kW-mo/yr
|
- | - | - | |
04 | 2.2136: Install / repair insulation on steam lines | $175 | $98 | - | - |
$175
-
MMBtu
|
- | - | |
05 | 2.8113: Purchase gas directly from a contract gas supplier | $5,397 | - | - | - | - | $5,397 | - | |
06 | 2.8112: Combine utility meters | $864 | $3,000 | - | - | - | $864 | - | |
07 | 2.8112: Combine utility meters | $3,442 | $3,000 | - | - | - | $3,442 | - | |
08 | 2.7111: Reduce illumination to minimum necessary levels | $5,379 | $149 |
$4,106
54,534
kWh
|
$1,153
-
kW-mo/yr
|
- | - | $120 | |
09 | 2.7447: Install vinyl strip / high speed / air curtain doors | $9,359 | $5,100 | - | - |
$9,359
-
MMBtu
|
- | - | |
10 | 2.7224: Reduce space conditioning during non-working hours | $1,007 | $1,050 |
$1,007
13,381
kWh
|
- | - | - | - | |
11 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $14,436 | $2,500 | - |
$14,436
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $56,594 | $19,047 |
$16,931
224,862
kWh
|
$20,306
-
kW-mo/yr
|
$9,534
-
MMBtu
|
$9,703 | $120 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs