ITAC Assessment: KU0498
ITAC logo
ITAC Assessment: KU0498
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product corrugated metal pipe
NAICS
n/a
SIC 3498: Fabricated Pipe and Pipe Fittings
Sales Range $10
M
to 50
M
# of Employees 18
Plant Area 84,250
ft2
Annual Production 9,000
ton
Production Hrs. Annual 2,750
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $45,299 1,208,675
kWh
Electricity Demand $29,470 7,263
kW-mo/yr
Natural Gas $49,882 8,694
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $33,480 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,940

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 2.4239: Eliminate or reduce compressed air usage $2,010 $4,150 $1,340
37,808
kWh
$670
-
kW-mo/yr
- - - - - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,610 $650 $1,090
29,308
kWh
$520
-
kW-mo/yr
- - - - - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $560 $570 $380
10,258
kWh
$180
-
kW-mo/yr
- - - - - -
04 2.4314: Use synthetic lubricant $360 $980 $220
5,862
kWh
$110
-
kW-mo/yr
- - - - $30 -
05 2.4221: Install compressor air intakes in coolest locations $340 $630 $230
6,155
kWh
$110
-
kW-mo/yr
- - - - - -
06 2.8114: Change rate schedules or other changes in utility service $320 - $180
1,758
kWh
- - - - $140 - -
07 2.4133: Use most efficient type of electric motors $250 $970 $170
4,396
kWh
$80
-
kW-mo/yr
- - - - - -
08 3.7393: Implement a machine and coolant sump cleaning program to minimize coolant contamination $3,150 $1,450 - - $2,460
-
gal
- - - $690 -
09 3.8132: Use less toxic and volatile solvent substitutes $2,930 $3,000 $(-200.0)
(-5,275)
kWh
$(-60.0)
-
kW-mo/yr
- $4,510
-
gal
- - $(-1,320.0) -
10 4.521: Clear and rent existing space $18,450 $12,710 - - - - - $18,450 - -
11 4.611: Begin a practice of predictive / preventative maintenance $1,960 $730 - - - - - - - $1,960
12 4.621: Use fixtures to reduce machine changeout times $1,540 $3,320 - - - - $1,540 - - -
TOTAL RECOMMENDED $33,480 $29,160 $3,410
90,270
kWh
$1,610
-
kW-mo/yr
$2,460
-
gal
$4,510
-
gal
$1,540 $18,590 $(-600.0) $1,960
TOTAL IMPLEMENTED $7,940 $4,030 $1,880
47,479
kWh
$810
-
kW-mo/yr
$2,460
-
gal
- - $140 $690 $1,960
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs