Assessment Year | 1997 |
---|---|
Principal Product | injection molded plastic parts |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 325 |
Plant Area |
420,000
ft2
|
Annual Production | 30,000,000
lb
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $984,525 | 29,803,635 |
kWh
|
$0.033 |
Electricity Demand | $265,541 | 63,684 |
kW-mo/yr
|
$4.17 |
Natural Gas | $65,492 | 11,838 |
MMBtu
|
$5.53 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $375,220 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $41,100 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system | $30,340 | $21,800 |
$30,340
919,402
kWh
|
- | - | - | - | - | |
02 | 2.2511: Insulate bare equipment | $24,670 | $27,000 |
$18,380
557,151
kWh
|
$6,290
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $8,190 | $25,840 |
$6,720
203,693
kWh
|
$1,470
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $3,890 | $650 |
$3,220
97,597
kWh
|
$670
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.7135: Install occupancy sensors | $2,780 | $1,500 |
$2,780
84,115
kWh
|
- | - | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $980 | $1,440 |
$260
7,913
kWh
|
$50
-
kW-mo/yr
|
- | - | $670 | - | |
07 | 3.8132: Use less toxic and volatile solvent substitutes | $5,460 | $16,500 |
$(-950.0)
(-29,015)
kWh
|
$(-330.0)
-
kW-mo/yr
|
$13,780
-
gal
|
- | - | $(-7,040.0) | |
08 | 4.621: Use fixtures to reduce machine changeout times | $298,910 | $17,200 | - | - | - |
$229,910
-
lb
|
$69,000 | - | |
TOTAL RECOMMENDED | $375,220 | $111,930 |
$60,750
1,840,856
kWh
|
$8,150
-
kW-mo/yr
|
$13,780
-
gal
|
$229,910
-
lb
|
$69,670 | $(-7,040.0) | ||
TOTAL IMPLEMENTED | $41,100 | $70,840 |
$26,930
815,944
kWh
|
$7,430
-
kW-mo/yr
|
$13,780
-
gal
|
- | - | $(-7,040.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs