ITAC Assessment: KU0428
ITAC logo
ITAC Assessment: KU0428
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product molded rubber products
NAICS
n/a
SIC 3061: Molded, Extruded, and Lathe-Cut Mechanical Rubber Goods
Sales Range $1
M
to 5
M
# of Employees 11
Plant Area 11,000
ft2
Annual Production 3,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $42,658 831,184
kWh
Natural Gas $1,693 331
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,735 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $770

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,624 $3,145 $1,624
31,653
kWh
-
02 2.7135: Install occupancy sensors $211 $250 $211
4,103
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $75 $600 $75
1,465
kWh
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $256 $450 $256
4,982
kWh
-
05 2.1311: Replace electrically-operated equipment with fossil fuel equipment $2,408 $26,000 $4,181
81,477
kWh
$(-1,773.0)
-
MMBtu
06 2.4314: Use synthetic lubricant $256 $136 $256
4,982
kWh
-
07 2.6231: Utilize controls to operate equipment only when needed $135 $70 $135
2,638
kWh
-
08 2.7447: Install vinyl strip / high speed / air curtain doors $304 $549 $60
1,172
kWh
$244
-
MMBtu
09 2.4235: Remove or close off unneeded compressed air lines $346 $105 $346
6,741
kWh
-
10 2.4221: Install compressor air intakes in coolest locations $120 $163 $120
2,345
kWh
-
TOTAL RECOMMENDED $5,735 $31,468 $7,264
141,558
kWh
$(-1,529.0)
-
MMBtu
TOTAL IMPLEMENTED $770 $817 $526
10,258
kWh
$244
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs