ITAC Assessment: KU0427
ITAC logo
ITAC Assessment: KU0427
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Livestock feed
NAICS
n/a
SIC 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats
Sales Range $10
M
to 50
M
# of Employees 21
Plant Area 65,600
ft2
Annual Production 100,000
ton
Production Hrs. Annual 4,800
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $162,280 2,676,729
kWh
Natural Gas $24,386 13,674
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,797 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,691

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,297 - $1,297
21,395
kWh
- -
02 2.7135: Install occupancy sensors $1,084 $1,980 $1,084
17,878
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,798 $828 $729
12,016
kWh
- $1,069
04 2.2164: Turn off steam tracing during mild weather $876 $2,400 - $876
-
MMBtu
-
05 2.7261: Install timers and/or thermostats $348 $100 $36
586
kWh
$312
-
MMBtu
-
06 2.4221: Install compressor air intakes in coolest locations $160 $107 $160
2,638
kWh
- -
07 2.4133: Use most efficient type of electric motors $5,234 $7,537 $5,234
64,771
kWh
- -
TOTAL RECOMMENDED $10,797 $12,952 $8,540
119,284
kWh
$1,188
-
MMBtu
$1,069
TOTAL IMPLEMENTED $6,691 $7,644 $6,691
88,804
kWh
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs