Assessment Year | 2025 |
---|---|
Principal Product | Forged and Heat Treated Aerospace Engine Components |
NAICS | 332111: Iron and Steel Forging |
SIC | 3462: Iron and Steel Forgings |
Sales Range | $50 M to 100M |
# of Employees | 150 |
Plant Area |
187,000
ft2
|
Annual Production | 500,000
units
|
Production Hrs. Annual | 7,224
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $571,553 | 10,206,327 |
kWh
|
$0.056 | |
Electricity Demand | $270,854 | 27,359 |
kW-mo/yr
|
$9.90 | |
Electricity Fees | $31,302 | - |
|
- | |
Natural Gas | $1,852,234 | 318,674 |
MMBtu
|
$5.81 | |
Waste Disposal Costs | |||||
Water Usage | $110,942 | 4,370 |
Tgal
|
$25.39 | |
TOTAL YEARLY COSTS | $2,836,885 | ||||
RECOMMENDED SAVINGS* | $298,821 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $59,878 | $637,500 |
$59,878
1,069,265
kWh
|
- | |
02 | 2.4314: Use synthetic lubricant | $4,748 | $60 |
$3,510
63,818
kWh
|
$1,238
-
kW-mo/yr
|
|
03 | 2.3212: Optimize plant power factor | $48,315 | $58,703 | - |
$48,315
-
kW-mo/yr
|
|
04 | 2.4239: Eliminate or reduce compressed air usage | $98,900 | $5,262 |
$98,900
1,760,000
kWh
|
- | |
05 | 2.7145: Install skylights | $3,050 | $7,200 |
$3,050
54,500
kWh
|
- | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $83,930 | $15,300 |
$82,300
1,470,000
kWh
|
$1,630
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $298,821 | $724,025 |
$247,638
4,417,583
kWh
|
$51,183
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs