| Assessment Year | 2005 |
|---|---|
| Principal Product | Ice cream |
| NAICS | 311520: Ice Cream and Frozen Dessert Manufacturing |
| SIC | 2024: Ice Cream and Frozen Desserts |
| Sales Range | $5 M to 10M |
| # of Employees | 67 |
| Plant Area |
58,600
ft2
|
| Annual Production | 8,000
Tgal
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $243,876 | 8,531,807 |
kWh
|
$0.029 |
| Electricity Demand | $271,377 | 36,865 |
kW-mo/yr
|
$7.36 |
| Electricity Fees | $5,035 | - |
|
- |
| Natural Gas | $49,810 | 8,829 |
MMBtu
|
$5.64 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $13,487 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $12,837 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,070 | $440 |
$4,120
144,400
kWh
|
$2,950
-
kW-mo/yr
|
- | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $355 | $416 |
$168
5,878
kWh
|
$187
-
kW-mo/yr
|
- | - | |
| 03 | 2.3191: Use demand controller or load shedder | $1,190 | $740 | - |
$1,190
-
kW-mo/yr
|
- | - | |
| 04 | 2.2711: Utilize outside air instead of conditioned air for drying | $1,180 | $810 |
$640
22,300
kWh
|
$540
-
kW-mo/yr
|
- | - | |
| 05 | 2.2511: Insulate bare equipment | $710 | $1,790 | - | - |
$710
-
MMBtu
|
- | |
| 06 | 2.7135: Install occupancy sensors | $1,760 | $2,260 |
$960
33,500
kWh
|
$800
-
kW-mo/yr
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $572 | $292 |
$372
13,015
kWh
|
$312
-
kW-mo/yr
|
- | $(-112.0) | |
| 08 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $650 | $4,550 |
$350
12,200
kWh
|
$300
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $13,487 | $11,298 |
$6,610
231,293
kWh
|
$6,279
-
kW-mo/yr
|
$710
-
MMBtu
|
$(-112.0) | ||
| TOTAL IMPLEMENTED | $12,837 | $6,748 |
$6,260
219,093
kWh
|
$5,979
-
kW-mo/yr
|
$710
-
MMBtu
|
$(-112.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs