ITAC Assessment: KU0424
ITAC logo
ITAC Assessment: KU0424
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Lubricating Oils
NAICS
n/a
SIC 2992: Lubricating Oils and Greases
Sales Range $50
M
to 100
M
# of Employees 27
Plant Area 100,000
ft2
Annual Production 16,500
Tgal
Production Hrs. Annual 2,500
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $93,845 1,361,665
kWh
Natural Gas $135,990 43,980
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,944 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $242 $3,578 $1,131
16,413
kWh
- $(-889.0)
02 2.7135: Install occupancy sensors $667 $450 $667
9,672
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $566 $1,534 $566
8,206
kWh
- -
04 2.4221: Install compressor air intakes in coolest locations $1,757 $375 $1,757
25,498
kWh
- -
05 2.6231: Utilize controls to operate equipment only when needed $556 $200 - $556
-
MMBtu
-
06 2.7314: Reduce ventilation air $156 - - $156
-
MMBtu
-
TOTAL RECOMMENDED $3,944 $6,137 $4,121
59,789
kWh
$712
-
MMBtu
$(-889.0)
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs