ITAC Assessment: KU0419
ITAC logo
ITAC Assessment: KU0419
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Corrugated Shipping Containers
NAICS
n/a
SIC 2653: Corrugated and Solid Fiber Boxes
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area 192,000
ft2
Annual Production 800,000
thousand feet
Production Hrs. Annual 6,600
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $231,958 4,209,261
kWh
Natural Gas $222,820 65,401
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $191,559 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,503

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $167,541 $640,000 - - $167,541
02 2.2511: Insulate bare equipment $4,443 $2,405 - $4,443
-
MMBtu
-
03 2.1213: Direct warmest air to combustion intake $10,041 $15,400 $(-727.0)
(-13,189)
kWh
$10,768
-
MMBtu
-
04 2.2135: Repair and eliminate steam leaks $3,075 $750 - $3,075
-
MMBtu
-
05 2.2511: Insulate bare equipment $2,124 $5,376 - $2,124
-
MMBtu
-
06 2.4221: Install compressor air intakes in coolest locations $2,907 $201 $2,907
56,272
kWh
- -
07 2.7447: Install vinyl strip / high speed / air curtain doors $1,428 $1,386 - $1,428
-
MMBtu
-
TOTAL RECOMMENDED $191,559 $665,518 $2,180
43,083
kWh
$21,838
-
MMBtu
$167,541
TOTAL IMPLEMENTED $4,503 $2,136 - $4,503
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings