Assessment Year | 1993 |
---|---|
Principal Product | industrial burners |
NAICS |
n/a
|
SIC | 3433: Heating Equipment, Except Electric and Warm Air Furnaces |
Sales Range | $10 M to 50M |
# of Employees | 148 |
Plant Area |
100,000
ft2
|
Annual Production | 8,000
pieces
|
Production Hrs. Annual | 1,700
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $37,754 | 673,505 |
kWh
|
$0.056 |
Natural Gas | $39,939 | 9,155 |
MMBtu
|
$4.36 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $4,949 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,818 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4226: Use / purchase optimum sized compressor | $997 | $2,350 |
$997
17,878
kWh
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $867 | $240 |
$867
16,120
kWh
|
- | |
03 | 2.2437: Recover waste heat from equipment | $375 | $1,301 | - |
$375
-
MMBtu
|
|
04 | 2.4221: Install compressor air intakes in coolest locations | $262 | $200 |
$262
4,689
kWh
|
- | |
05 | 2.7224: Reduce space conditioning during non-working hours | $884 | $1,000 |
$577
10,551
kWh
|
$307
-
MMBtu
|
|
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $629 | $2,133 |
$629
7,327
kWh
|
- | |
07 | 2.6231: Utilize controls to operate equipment only when needed | $621 | $200 |
$621
11,137
kWh
|
- | |
08 | 2.6218: Turn off equipment when not in use | $153 | $551 | - |
$153
-
MMBtu
|
|
09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $161 | $480 |
$161
2,931
kWh
|
- | |
TOTAL RECOMMENDED | $4,949 | $8,455 |
$4,114
70,633
kWh
|
$835
-
MMBtu
|
||
TOTAL IMPLEMENTED | $1,818 | $2,772 |
$1,290
23,740
kWh
|
$528
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs