ITAC Assessment: AM0265
ITAC logo
ITAC Assessment: AM0265
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Chemical laboratory molded epoxy sinks and work surfaces
NAICS
n/a
SIC 3821: Laboratory Apparatus and Furniture
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 75,000
ft2
Annual Production 132,000
pieces
Production Hrs. Annual 4,301
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $82,022 2,220,692
kWh
Electricity Demand $44,074 5,403
kW-mo/yr
Electricity Fees $1,193 -
Natural Gas $40,022 10,043
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,980 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,110

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings
01 3.6192: Use a less expensive method of waste removal $3,100 $750 - - - $3,100 -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,260 $760 $660
23,740
kWh
$600
-
kW-mo/yr
- - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,550 $240 $1,550
55,393
kWh
- - - -
04 2.8123: Pay utility bills on time $1,010 - - - - - $1,010
05 2.2437: Recover waste heat from equipment $860 $380 - - $860
-
MMBtu
- -
06 2.7124: Make a practice of turning off lights when not needed $200 $300 $200
7,327
kWh
- - - -
TOTAL RECOMMENDED $7,980 $2,430 $2,410
86,460
kWh
$600
-
kW-mo/yr
$860
-
MMBtu
$3,100 $1,010
TOTAL IMPLEMENTED $6,110 $2,050 $2,410
86,460
kWh
$600
-
kW-mo/yr
- $3,100 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs