Assessment Year | 1992 |
---|---|
Principal Product | BRAKE ACTUATORS, ETC |
NAICS |
n/a
|
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $50 M to 100M |
# of Employees | 475 |
Plant Area |
n/a
|
Annual Production | 3,300,000
pieces
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $381,552 | 7,157,093 |
kWh
|
$0.053 |
Natural Gas | $64,063 | 14,947 |
MMBtu
|
$4.29 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $41,594 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,156 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.8113: Purchase gas directly from a contract gas supplier | $24,157 | - | - |
$24,157
-
MMBtu
|
- | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,781 | $17,843 |
$5,781
108,441
kWh
|
- | - | |
03 | 2.2437: Recover waste heat from equipment | $3,530 | $3,400 |
$3,530
66,237
kWh
|
- | - | |
04 | 2.2521: Isolate steam lines to avoid heating air conditioned areas | $1,078 | $59,000 |
$1,078
20,223
kWh
|
- | - | |
05 | 2.7261: Install timers and/or thermostats | $1,892 | $925 |
$1,296
24,326
kWh
|
$596
-
MMBtu
|
- | |
06 | 2.4221: Install compressor air intakes in coolest locations | $3,155 | $630 |
$3,155
59,203
kWh
|
- | - | |
07 | 2.4227: Use compressor air filters | $851 | - |
$931
16,120
kWh
|
- | $(-80.0) | |
08 | 2.4133: Use most efficient type of electric motors | $182 | $480 |
$182
3,517
kWh
|
- | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $172 | - |
$375
7,034
kWh
|
- | $(-203.0) | |
10 | 2.6232: Install set-back timers | $515 | $900 |
$515
9,672
kWh
|
- | - | |
11 | 2.6232: Install set-back timers | $281 | $91 |
$281
5,275
kWh
|
- | - | |
TOTAL RECOMMENDED | $41,594 | $83,269 |
$17,124
320,048
kWh
|
$24,753
-
MMBtu
|
$(-283.0) | ||
TOTAL IMPLEMENTED | $17,156 | $83,178 |
$16,843
314,773
kWh
|
$596
-
MMBtu
|
$(-283.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs