| Assessment Year | 1992 |
|---|---|
| Principal Product | PAPER BAGS |
| NAICS |
n/a
|
| SIC | 2673: Plastics, Foil, and Coated Paper Bags |
| Sales Range | $5 M to 10M |
| # of Employees | 50 |
| Plant Area |
n/a
|
| Annual Production | 14,000,000
pieces
|
| Production Hrs. Annual | 4,250
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $66,093 | 902,696 |
kWh
|
$0.073 |
| Natural Gas | $1,865 | 423 |
MMBtu
|
$4.41 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $4,869 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,647 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7221: Lower temperature during the winter season and vice-versa | $1,545 | $20 |
$1,545
21,102
kWh
|
- | - | |
| 02 | 2.7229: Air condition only space necessary | $472 | $2,300 |
$472
6,448
kWh
|
- | - | |
| 03 | 2.7211: Clean and maintain refrigerant condensers and towers | $150 | $30 |
$150
2,052
kWh
|
- | - | |
| 04 | 2.6232: Install set-back timers | $751 | $700 |
$751
10,258
kWh
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $83 | - |
$107
1,465
kWh
|
- | $(-24.0) | |
| 06 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $667 | - |
$667
-
kWh
|
- | - | |
| 07 | 2.2437: Recover waste heat from equipment | $450 | $716 | - |
$450
-
MMBtu
|
- | |
| 08 | 2.4221: Install compressor air intakes in coolest locations | $322 | - |
$322
4,396
kWh
|
- | - | |
| 09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $429 | $1,400 |
$429
5,862
kWh
|
- | - | |
| TOTAL RECOMMENDED | $4,869 | $5,166 |
$4,443
51,583
kWh
|
$450
-
MMBtu
|
$(-24.0) | ||
| TOTAL IMPLEMENTED | $3,647 | $2,866 |
$3,197
43,670
kWh
|
$450
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs