ITAC Assessment: KU0331
ITAC logo
ITAC Assessment: KU0331
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product INDUSTRIAL PAINT
NAICS
n/a
SIC 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products
Sales Range $10
M
to 50
M
# of Employees 95
Plant Area
n/a
Annual Production 1,750
Tgal
Production Hrs. Annual 3,875
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $154,545 1,760,258
kWh
Natural Gas $64,999 16,363
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,016 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $628 $395 $628
8,206
kWh
-
02 2.7121: Utilize daylight whenever possible in lieu of artificial light $181 $500 $181
2,345
kWh
-
03 2.6232: Install set-back timers $2,630 $2,500 $2,630
33,998
kWh
-
04 2.2443: Re-use or recycle hot or cold process exhaust air $3,445 $10,200 $(-227.0)
(-2,931)
kWh
$3,672
-
MMBtu
05 2.7447: Install vinyl strip / high speed / air curtain doors $2,394 $6,500 - $2,394
-
MMBtu
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,020 - $1,020
13,189
kWh
-
07 2.2437: Recover waste heat from equipment $5,925 $14,000 - $5,925
-
MMBtu
08 2.4312: Improve lubrication practices $793 - $793
10,258
kWh
-
TOTAL RECOMMENDED $17,016 $34,095 $5,025
65,065
kWh
$11,991
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs