ITAC Assessment: CO0523
ITAC logo
ITAC Assessment: CO0523
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Concrete pipe & prestressed concrete products
NAICS 327332: Concrete Pipe Manufacturing
SIC 3272: Concrete Products, Except Block and Brick
Sales Range $100
M
to 500
M
# of Employees 135
Plant Area 46,800
ft2
Annual Production 230,000
ton
Production Hrs. Annual 5,408
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $32,308 1,959,601
kWh
Electricity Demand $99,441 7,893
kW-mo/yr
Electricity Fees $1,665 -
Natural Gas $175,144 32,217
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $46,726 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,120

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.4239: Eliminate or reduce compressed air usage $19,740 $12,000 $5,350
232,900
kWh
$14,390
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $10,270 $19,440 $4,440
193,300
kWh
$5,680
-
kW-mo/yr
- $150
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,990 $230 $3,380
147,300
kWh
$4,330
-
kW-mo/yr
- $(-720.0)
04 2.7142: Utilize higher efficiency lamps and/or ballasts $4,122 $12,500 $2,228
97,070
kWh
$2,090
-
kW-mo/yr
- $(-196.0)
05 2.7243: Improve air circulation with destratification fans / other methods $4,120 $11,840 $(-160.0)
(-6,800)
kWh
$(-120.0)
-
kW-mo/yr
$4,400
-
MMBtu
-
06 2.2135: Repair and eliminate steam leaks $1,130 $210 - - $1,130
-
MMBtu
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $144 $266 $40
1,710
kWh
$92
-
kW-mo/yr
- $12
08 2.7142: Utilize higher efficiency lamps and/or ballasts $210 $490 $110
4,806
kWh
$144
-
kW-mo/yr
- $(-44.0)
TOTAL RECOMMENDED $46,726 $56,976 $15,388
670,286
kWh
$26,606
-
kW-mo/yr
$5,530
-
MMBtu
$(-798.0)
TOTAL IMPLEMENTED $8,120 $440 $3,380
147,300
kWh
$4,330
-
kW-mo/yr
$1,130
-
MMBtu
$(-720.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs