| Assessment Year | 1990 |
|---|---|
| Principal Product | GRAY IRON CASTINGS |
| NAICS |
n/a
|
| SIC | 3321: Gray and Ductile Iron Foundries |
| Sales Range | $5 M to 10M |
| # of Employees | 105 |
| Plant Area |
n/a
|
| Annual Production | 2,900
ton
|
| Production Hrs. Annual | 4,700
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $125,784 | 1,527,843 |
kWh
|
$0.082 |
| Natural Gas | $64,982 | 41,468 |
MMBtu
|
$1.57 |
| Other Energy | $146,635 | 22,594 |
MMBtu
|
$6.49 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $83,212 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $65,296 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Energy Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2414: Use waste heat from hot flue gases to preheat | $16,128 | $20,800 | - | - |
$16,128
-
MMBtu
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,200 | $3,078 |
$4,438
53,927
kWh
|
- | - | $762 | |
| 03 | 2.2531: Re-size charging openings or add movable cover or door | $391 | $466 | - |
$391
-
MMBtu
|
- | - | |
| 04 | 2.7261: Install timers and/or thermostats | $1,788 | $2,802 | - |
$1,788
-
MMBtu
|
- | - | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $675 | $1,416 |
$675
8,206
kWh
|
- | - | - | |
| 06 | 2.7314: Reduce ventilation air | $8,297 | $11,700 |
$4,607
55,979
kWh
|
$3,690
-
MMBtu
|
- | - | |
| 07 | 2.6222: Use drying oven (batch type) on alternate days or other optimum schedule to run equipment with full loads | $50,733 | - | - |
$15,072
-
MMBtu
|
$26,661
-
MMBtu
|
$9,000 | |
| TOTAL RECOMMENDED | $83,212 | $40,262 |
$9,720
118,112
kWh
|
$20,941
-
MMBtu
|
$42,789
-
MMBtu
|
$9,762 | ||
| TOTAL IMPLEMENTED | $65,296 | $16,660 |
$9,720
118,112
kWh
|
$19,153
-
MMBtu
|
$26,661
-
MMBtu
|
$9,762 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Other Energy Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs