ITAC Assessment: KU0316
ITAC logo
ITAC Assessment: KU0316
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product FLUIDS FOR AUTO INDUSTRY
NAICS
n/a
SIC 2992: Lubricating Oils and Greases
Sales Range $10
M
to 50
M
# of Employees 85
Plant Area
n/a
Annual Production 20,000,000
pieces
Production Hrs. Annual 7,200
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $216,092 4,340,856
kWh
Natural Gas $25,705 6,494
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,834 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,727

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.6232: Install set-back timers $3,487 $2,075 $3,487
70,047
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $924 $1,005 $924
18,464
kWh
- -
03 2.2614: Use cooling tower or economizer to replace chiller cooling $7,122 $15,000 $7,362
148,007
kWh
- $(-240.0)
04 2.2621: Modify refrigeration system to operate at a lower pressure $4,990 $7,200 $4,990
100,234
kWh
- -
05 2.3212: Optimize plant power factor $2,160 $2,250 $2,160
-
kWh
- -
06 2.7447: Install vinyl strip / high speed / air curtain doors $1,034 $1,000 - $1,034
-
MMBtu
-
07 2.6121: Reduce hot water temperature to the minimum required $117 - $117
2,345
kWh
- -
TOTAL RECOMMENDED $19,834 $28,530 $19,040
339,097
kWh
$1,034
-
MMBtu
$(-240.0)
TOTAL IMPLEMENTED $14,727 $21,330 $13,933
236,518
kWh
$1,034
-
MMBtu
$(-240.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs