ITAC Assessment: KU0256
ITAC logo
ITAC Assessment: KU0256
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product ELECTRICAL CONTRACTORS
NAICS
n/a
SIC 3643: Current-Carrying Wiring Devices
Sales Range $10
M
to 50
M
# of Employees 285
Plant Area
n/a
Annual Production 2,700,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $119,129 2,932,884
kWh
Natural Gas $23,193 5,780
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,802 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,063

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $9,474 $8,895 $9,474
233,294
kWh
- -
02 2.7261: Install timers and/or thermostats $7,001 - - $7,001
-
MMBtu
-
03 2.4312: Improve lubrication practices $452 - $452
11,137
kWh
- -
04 2.1233: Analyze flue gas for proper air/fuel ratio $301 - - $501
-
MMBtu
$(-200.0)
05 2.4221: Install compressor air intakes in coolest locations $309 $600 $309
7,620
kWh
- -
06 2.6121: Reduce hot water temperature to the minimum required $265 - - $265
-
MMBtu
-
TOTAL RECOMMENDED $17,802 $9,495 $10,235
252,051
kWh
$7,767
-
MMBtu
$(-200.0)
TOTAL IMPLEMENTED $8,063 $600 $761
18,757
kWh
$7,502
-
MMBtu
$(-200.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs