| Assessment Year | 1987 |
|---|---|
| Principal Product | GASKET DIE CUTS |
| NAICS |
n/a
|
| SIC | 3053: Gaskets, Packing, and Sealing Devices |
| Sales Range | $5 M to 10M |
| # of Employees | 75 |
| Plant Area |
n/a
|
| Annual Production | 65,000,000
pieces
|
| Production Hrs. Annual | 2,125
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $31,629 | 350,234 |
kWh
|
$0.090 |
| Natural Gas | $6,679 | 1,438 |
MMBtu
|
$4.64 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $7,554 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,424 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,553 | $2,059 |
$4,553
50,410
kWh
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $847 | $100 |
$847
9,379
kWh
|
- | - | |
| 03 | 2.7261: Install timers and/or thermostats | $809 | $40 |
$159
1,758
kWh
|
$650
-
MMBtu
|
- | |
| 04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $445 | $600 |
$556
6,155
kWh
|
$(-111.0)
-
MMBtu
|
- | |
| 05 | 2.4312: Improve lubrication practices | $424 | $600 |
$424
4,689
kWh
|
- | - | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $212 | $120 |
$212
2,345
kWh
|
- | - | |
| 07 | 2.6121: Reduce hot water temperature to the minimum required | $211 | - |
$164
1,758
kWh
|
$47
-
MMBtu
|
- | |
| 08 | 2.4221: Install compressor air intakes in coolest locations | $132 | $250 |
$132
1,465
kWh
|
- | - | |
| 09 | 2.1233: Analyze flue gas for proper air/fuel ratio | $(-79.0) | - | - |
$121
-
MMBtu
|
$(-200.0) | |
| TOTAL RECOMMENDED | $7,554 | $3,769 |
$7,047
77,959
kWh
|
$707
-
MMBtu
|
$(-200.0) | ||
| TOTAL IMPLEMENTED | $2,424 | $860 |
$1,806
19,929
kWh
|
$818
-
MMBtu
|
$(-200.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs