Assessment Year | 1985 |
---|---|
Principal Product | HEAVY CONSTRUCTION EQUIP |
NAICS |
n/a
|
SIC | 3531: Construction Machinery and Equipment |
Sales Range | $5 M to 10M |
# of Employees | 51 |
Plant Area |
n/a
|
Annual Production | 100,000
pieces
|
Production Hrs. Annual | 2,134
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $25,410 | 280,481 |
kWh
|
$0.091 |
Natural Gas | $15,601 | 3,216 |
MMBtu
|
$4.85 |
Fuel Oil #2 | $2,800 | 392 |
MMBtu
|
$7.14 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $16,119 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $15,120 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $10,250 | $80 |
$584
6,448
kWh
|
$9,666
-
MMBtu
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,664 | $3,439 |
$3,664
40,445
kWh
|
- | - | |
03 | 2.1123: Install automatic stack damper | $1,057 | $800 | - |
$1,057
-
MMBtu
|
- | |
04 | 2.7441: Replace broken windows and/or window sash | $999 | $750 | - |
$999
-
MMBtu
|
- | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $149 | - | - |
$364
-
MMBtu
|
$(-215.0) | |
TOTAL RECOMMENDED | $16,119 | $5,069 |
$4,248
46,893
kWh
|
$12,086
-
MMBtu
|
$(-215.0) | ||
TOTAL IMPLEMENTED | $15,120 | $4,319 |
$4,248
46,893
kWh
|
$11,087
-
MMBtu
|
$(-215.0) |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs