Assessment Year | 1984 |
---|---|
Principal Product | PRINTED MATERIAL |
NAICS |
n/a
|
SIC | 2759: Commercial Printing, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 170 |
Plant Area |
n/a
|
Annual Production | 12,000,000
lb
|
Production Hrs. Annual | 6,600
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $190,835 | 2,881,887 |
kWh
|
$0.066 |
Natural Gas | $32,944 | 6,722 |
MMBtu
|
$4.90 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $38,457 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,051 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2422: Use waste heat from hot flue gases to generate steam | $15,513 | $17,900 | - |
$15,513
-
MMBtu
|
- | |
02 | 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle | $8,554 | $18,500 |
$5,856
40,739
kWh
|
$2,698
-
MMBtu
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,281 | $200 |
$1,281
19,343
kWh
|
- | - | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $4,270 | $235 |
$4,270
64,478
kWh
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,310 | $170 |
$2,310
34,877
kWh
|
- | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,902 | $30 |
$1,902
28,722
kWh
|
- | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $485 | $350 |
$485
7,327
kWh
|
- | - | |
08 | 2.1233: Analyze flue gas for proper air/fuel ratio | $975 | $1,000 | - |
$1,475
-
MMBtu
|
$(-500.0) | |
09 | 2.1123: Install automatic stack damper | $897 | $2,000 | - |
$897
-
MMBtu
|
- | |
10 | 2.1222: Install turbulators | $289 | $650 | - |
$289
-
MMBtu
|
- | |
11 | 2.1242: Minimize boiler blowdown with better feedwater treatment | $162 | - | - |
$162
-
MMBtu
|
- | |
12 | 2.1242: Minimize boiler blowdown with better feedwater treatment | $109 | - | - |
$309
-
MMBtu
|
$(-200.0) | |
13 | 2.1233: Analyze flue gas for proper air/fuel ratio | $396 | - | - |
$946
-
MMBtu
|
$(-550.0) | |
14 | 2.6124: Establish equipment maintenance schedule | $330 | - |
$990
14,947
kWh
|
- | $(-660.0) | |
15 | 2.1123: Install automatic stack damper | $461 | $800 | - |
$461
-
MMBtu
|
- | |
16 | 2.6214: Shut off pilots in standby equipment | $136 | - | - |
$186
-
MMBtu
|
$(-50.0) | |
17 | 2.6121: Reduce hot water temperature to the minimum required | $147 | - | - |
$147
-
MMBtu
|
- | |
18 | 2.2122: Install / repair insulation on condensate lines | $127 | $63 | - |
$127
-
MMBtu
|
- | |
19 | 2.7444: Close holes and openings in building such as broken windows | $113 | $39 |
$6
293
kWh
|
$107
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $38,457 | $41,937 |
$17,100
210,726
kWh
|
$23,317
-
MMBtu
|
$(-1,960.0) | ||
TOTAL IMPLEMENTED | $5,051 | $759 |
$5,072
76,787
kWh
|
$1,239
-
MMBtu
|
$(-1,260.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs