Assessment Year | 1984 |
---|---|
Principal Product | PET FOOD, TIN CANS |
NAICS |
n/a
|
SIC | 3411: Metal Cans |
Sales Range | $10 M to 50M |
# of Employees | 55 |
Plant Area |
n/a
|
Annual Production | 63,000,000
lb
|
Production Hrs. Annual | 2,740
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $130,260 | 2,038,101 |
kWh
|
$0.064 |
Natural Gas | $163,907 | 40,656 |
MMBtu
|
$4.03 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $84,823 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $32,215 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $6,577 | $9,000 | - |
$6,577
-
MMBtu
|
- | |
02 | 2.2511: Insulate bare equipment | $7,153 | $21,500 | - |
$7,153
-
MMBtu
|
- | |
03 | 3.6122: Install solid waste incinerator for heat | $25,600 | $40,000 | - |
$14,300
-
MMBtu
|
$11,300 | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $9,121 | - |
$9,121
142,732
kWh
|
- | - | |
05 | 2.4312: Improve lubrication practices | $6,312 | $600 |
$6,312
98,769
kWh
|
- | - | |
06 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $6,561 | $5,090 | - |
$6,561
-
MMBtu
|
- | |
07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,950 | $5,000 | - |
$2,950
-
MMBtu
|
- | |
08 | 2.2122: Install / repair insulation on condensate lines | $399 | $339 | - |
$399
-
MMBtu
|
- | |
09 | 2.2135: Repair and eliminate steam leaks | $830 | - | - |
$830
-
MMBtu
|
- | |
10 | 2.7447: Install vinyl strip / high speed / air curtain doors | $7,572 | $4,570 | - |
$7,572
-
MMBtu
|
- | |
11 | 2.7261: Install timers and/or thermostats | $2,648 | - |
$2,060
32,239
kWh
|
$588
-
MMBtu
|
- | |
12 | 2.7243: Improve air circulation with destratification fans / other methods | $1,060 | $2,000 |
$(-169.0)
(-2,638)
kWh
|
$1,229
-
MMBtu
|
- | |
13 | 2.2441: Preheat boiler makeup water with waste process heat | $3,949 | $3,200 | - |
$3,949
-
MMBtu
|
- | |
14 | 2.4221: Install compressor air intakes in coolest locations | $1,068 | $800 |
$1,068
16,706
kWh
|
- | - | |
15 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $618 | - |
$618
9,672
kWh
|
- | - | |
16 | 2.4239: Eliminate or reduce compressed air usage | $131 | - |
$131
2,052
kWh
|
- | - | |
17 | 2.2511: Insulate bare equipment | $1,757 | $2,100 | - |
$1,757
-
MMBtu
|
- | |
18 | 2.6121: Reduce hot water temperature to the minimum required | $150 | - |
$150
2,345
kWh
|
- | - | |
19 | 2.2694: Use highest temperature for chilling or cold storage | $262 | - |
$262
4,103
kWh
|
- | - | |
20 | 2.6214: Shut off pilots in standby equipment | $105 | - | - |
$105
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $84,823 | $94,199 |
$19,553
305,980
kWh
|
$53,970
-
MMBtu
|
$11,300 | ||
TOTAL IMPLEMENTED | $32,215 | $13,829 |
$19,553
305,980
kWh
|
$12,662
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs