ITAC Assessment: KU0112
ITAC logo
ITAC Assessment: KU0112
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1984
Principal Product MOUNTED CRANES
NAICS
n/a
SIC 3531: Construction Machinery and Equipment
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area
n/a
Annual Production 2,500
pieces
Production Hrs. Annual 5,000
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $87,009 1,541,618
kWh
Natural Gas $39,611 7,582
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $37,920 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $25,079

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7261: Install timers and/or thermostats $18,588 $1,074 - $18,588
-
MMBtu
-
02 2.6212: Turn off equipment during breaks, reduce operating time $3,459 - $463
8,206
kWh
$2,996
-
MMBtu
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $7,757 $12,786 $7,757
137,456
kWh
- -
04 2.1233: Analyze flue gas for proper air/fuel ratio $795 $200 - $1,195
-
MMBtu
$(-400.0)
05 2.1233: Analyze flue gas for proper air/fuel ratio $398 $400 - $548
-
MMBtu
$(-150.0)
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,012 $2,800 $5,012
88,804
kWh
- -
07 2.6212: Turn off equipment during breaks, reduce operating time $1,000 $360 $1,000
17,878
kWh
- -
08 2.6121: Reduce hot water temperature to the minimum required $286 - - $286
-
MMBtu
-
09 2.4221: Install compressor air intakes in coolest locations $625 $300 $625
11,137
kWh
- -
TOTAL RECOMMENDED $37,920 $17,920 $14,857
263,481
kWh
$23,613
-
MMBtu
$(-550.0)
TOTAL IMPLEMENTED $25,079 $4,474 $5,012
88,804
kWh
$20,617
-
MMBtu
$(-550.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs