| Assessment Year | 1983 |
|---|---|
| Principal Product | LEAD ACID BATTERIES |
| NAICS |
n/a
|
| SIC | 3691: Storage Batteries |
| Sales Range | $5 M to 10M |
| # of Employees | 60 |
| Plant Area |
n/a
|
| Annual Production | 60,000
pieces
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $149,771 | 2,296,307 |
kWh
|
$0.065 |
| Natural Gas | $65,242 | 12,689 |
MMBtu
|
$5.14 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,432 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $17,912 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $760 | $400 | - |
$760
-
MMBtu
|
|
| 02 | 2.3212: Optimize plant power factor | $6,604 | $16,000 |
$6,604
-
kWh
|
- | |
| 03 | 2.7261: Install timers and/or thermostats | $4,071 | $300 | - |
$4,071
-
MMBtu
|
|
| 04 | 2.7261: Install timers and/or thermostats | $1,414 | $400 | - |
$1,414
-
MMBtu
|
|
| 05 | 2.7221: Lower temperature during the winter season and vice-versa | $872 | $132 |
$229
3,517
kWh
|
$643
-
MMBtu
|
|
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,351 | $6,314 |
$2,351
36,049
kWh
|
- | |
| 07 | 2.7441: Replace broken windows and/or window sash | $1,840 | $52 | - |
$1,840
-
MMBtu
|
|
| 08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $191 | - |
$191
2,931
kWh
|
- | |
| 09 | 2.6121: Reduce hot water temperature to the minimum required | $329 | - | - |
$329
-
MMBtu
|
|
| TOTAL RECOMMENDED | $18,432 | $23,598 |
$9,375
42,497
kWh
|
$9,057
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $17,912 | $23,598 |
$9,184
39,566
kWh
|
$8,728
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs