ITAC Assessment: KU0108
ITAC logo
ITAC Assessment: KU0108
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product LEAD ACID BATTERIES
NAICS
n/a
SIC 3691: Storage Batteries
Sales Range $5
M
to 10
M
# of Employees 60
Plant Area
n/a
Annual Production 60,000
pieces
Production Hrs. Annual 8,400
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $149,771 2,296,307
kWh
Natural Gas $65,242 12,689
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,432 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,912

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $760 $400 - $760
-
MMBtu
02 2.3212: Optimize plant power factor $6,604 $16,000 $6,604
-
kWh
-
03 2.7261: Install timers and/or thermostats $4,071 $300 - $4,071
-
MMBtu
04 2.7261: Install timers and/or thermostats $1,414 $400 - $1,414
-
MMBtu
05 2.7221: Lower temperature during the winter season and vice-versa $872 $132 $229
3,517
kWh
$643
-
MMBtu
06 2.7142: Utilize higher efficiency lamps and/or ballasts $2,351 $6,314 $2,351
36,049
kWh
-
07 2.7441: Replace broken windows and/or window sash $1,840 $52 - $1,840
-
MMBtu
08 2.4231: Reduce the pressure of compressed air to the minimum required $191 - $191
2,931
kWh
-
09 2.6121: Reduce hot water temperature to the minimum required $329 - - $329
-
MMBtu
TOTAL RECOMMENDED $18,432 $23,598 $9,375
42,497
kWh
$9,057
-
MMBtu
TOTAL IMPLEMENTED $17,912 $23,598 $9,184
39,566
kWh
$8,728
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs