| Assessment Year | 1983 |
|---|---|
| Principal Product | AUTO PARTS |
| NAICS |
n/a
|
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $10 M to 50M |
| # of Employees | 350 |
| Plant Area |
n/a
|
| Annual Production | 9,000,000
pieces
|
| Production Hrs. Annual | 5,640
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $95,735 | 2,072,392 |
kWh
|
$0.046 |
| Natural Gas | $33,406 | 6,641 |
MMBtu
|
$5.03 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $36,900 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $840 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $487 | $150 |
$487
10,551
kWh
|
- | |
| 02 | 2.6124: Establish equipment maintenance schedule | $636 | $375 |
$636
13,775
kWh
|
- | |
| 03 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,124 | - |
$1,124
24,326
kWh
|
- | |
| 04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,926 | $1,260 | - |
$1,926
-
MMBtu
|
|
| 05 | 2.1123: Install automatic stack damper | $2,414 | $4,100 | - |
$2,414
-
MMBtu
|
|
| 06 | 2.2515: Use optimum thickness insulation | $498 | $100 | - |
$498
-
MMBtu
|
|
| 07 | 2.2437: Recover waste heat from equipment | $1,846 | $1,000 |
$1,846
107,562
kWh
|
- | |
| 08 | 2.7441: Replace broken windows and/or window sash | $342 | $80 | - |
$342
-
MMBtu
|
|
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,291 | $7,951 |
$13,291
287,808
kWh
|
- | |
| 10 | 2.7261: Install timers and/or thermostats | $12,782 | $10 |
$203
4,396
kWh
|
$12,579
-
MMBtu
|
|
| 11 | 2.7314: Reduce ventilation air | $1,554 | - | - |
$1,554
-
MMBtu
|
|
| TOTAL RECOMMENDED | $36,900 | $15,026 |
$17,587
448,418
kWh
|
$19,313
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $840 | $180 | - |
$840
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs