ITAC Assessment: KU0091
ITAC logo
ITAC Assessment: KU0091
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product ICE MACHINES
NAICS
n/a
SIC 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment
Sales Range $1
M
to 5
M
# of Employees 44
Plant Area
n/a
Annual Production 1,500
pieces
Production Hrs. Annual 2,080
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $16,640 346,424
kWh
Natural Gas $6,224 1,202
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,793 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,478 $912 $1,478
30,774
kWh
-
02 2.7261: Install timers and/or thermostats $1,331 $400 - $1,331
-
MMBtu
03 2.7447: Install vinyl strip / high speed / air curtain doors $461 $522 - $461
-
MMBtu
04 2.1123: Install automatic stack damper $300 $300 - $300
-
MMBtu
05 2.1233: Analyze flue gas for proper air/fuel ratio $223 $90 - $223
-
MMBtu
TOTAL RECOMMENDED $3,793 $2,224 $1,478
30,774
kWh
$2,315
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs