Assessment Year | 1982 |
---|---|
Principal Product | BOTTLED CARBONATED BEVERAGES |
NAICS |
n/a
|
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
n/a
|
Annual Production | 5,400,000
pieces
|
Production Hrs. Annual | 2,016
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $170,592 | 2,840,856 |
kWh
|
$0.060 |
Natural Gas | $61,477 | 21,117 |
MMBtu
|
$2.91 |
Other Energy | $300,266 | 35,979 |
MMBtu
|
$8.35 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $77,817 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Energy Savings |
---|---|---|---|---|---|---|---|
01 | 2.1335: Replace gasoline with diesel, lpg, or natural gas | $26,510 | $35,000 | - | - |
$26,510
-
MMBtu
|
|
02 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $18,206 | $7,700 |
$18,206
303,341
kWh
|
- | - | |
03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $7,081 | $2,129 | - |
$7,081
-
MMBtu
|
- | |
04 | 2.3191: Use demand controller or load shedder | $2,511 | $3,000 |
$2,511
-
kWh
|
- | - | |
05 | 2.8226: Increase efficiency of trucks | $9,000 | - | - | - |
$9,000
-
MMBtu
|
|
06 | 2.2437: Recover waste heat from equipment | $7,569 | $25,000 | - |
$7,569
-
MMBtu
|
- | |
07 | 2.7261: Install timers and/or thermostats | $6,940 | $100 |
$1,754
29,308
kWh
|
$5,186
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $77,817 | $72,929 |
$22,471
332,649
kWh
|
$19,836
-
MMBtu
|
$35,510
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Other Energy Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs