Assessment Year | 1996 |
---|---|
Principal Product | Pre-stressed Concrete |
NAICS |
n/a
|
SIC | 3272: Concrete Products, Except Block and Brick |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
7,890
ft2
|
Annual Production | 62,400
ton
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $109,208 | 2,418,230 |
kWh
|
$0.045 |
Electricity Demand | $54,427 | 8,184 |
kW-mo/yr
|
$6.65 |
Electricity Fees | $600 | - |
|
- |
LPG | $164,354 | 29,212 |
MMBtu
|
$5.63 |
Fuel Oil #2 | $56,924 | 10,872 |
MMBtu
|
$5.24 |
Fuel Oil #6 | $41,859 | 14,606 |
MMBtu
|
$2.87 |
Other Energy | $7,282 | 1,599 |
MMBtu
|
$4.55 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,707 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,539 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $481 | $585 |
$481
10,551
kWh
|
- | |
02 | 2.4133: Use most efficient type of electric motors | $2,071 | $4,256 |
$1,409
16,706
kWh
|
$662
-
kW-mo/yr
|
|
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $468 | $1,137 |
$248
5,569
kWh
|
$220
-
kW-mo/yr
|
|
04 | 3.6194: Ship hydraulic oil to secondary fuel program | $8,687 | $3,395 |
$7,127
157,679
kWh
|
$1,560
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $11,707 | $9,373 |
$9,265
190,505
kWh
|
$2,442
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $2,539 | $5,393 |
$1,657
22,275
kWh
|
$882
-
kW-mo/yr
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs