ITAC Assessment: OD0049
ITAC logo
ITAC Assessment: OD0049
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Pre-stressed Concrete
NAICS
n/a
SIC 3272: Concrete Products, Except Block and Brick
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 7,890
ft2
Annual Production 62,400
ton
Production Hrs. Annual 2,000
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $109,208 2,418,230
kWh
Electricity Demand $54,427 8,184
kW-mo/yr
Electricity Fees $600 -
LPG $164,354 29,212
MMBtu
Fuel Oil #2 $56,924 10,872
MMBtu
Fuel Oil #6 $41,859 14,606
MMBtu
Other Energy $7,282 1,599
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,707 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,539

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7261: Install timers and/or thermostats $481 $585 $481
10,551
kWh
-
02 2.4133: Use most efficient type of electric motors $2,071 $4,256 $1,409
16,706
kWh
$662
-
kW-mo/yr
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $468 $1,137 $248
5,569
kWh
$220
-
kW-mo/yr
04 3.6194: Ship hydraulic oil to secondary fuel program $8,687 $3,395 $7,127
157,679
kWh
$1,560
-
kW-mo/yr
TOTAL RECOMMENDED $11,707 $9,373 $9,265
190,505
kWh
$2,442
-
kW-mo/yr
TOTAL IMPLEMENTED $2,539 $5,393 $1,657
22,275
kWh
$882
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs