ITAC Assessment: KU0022
ITAC logo
ITAC Assessment: KU0022
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1981
Principal Product PRINTED PAPER PRODUCTS
NAICS
n/a
SIC 2759: Commercial Printing, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 80
Plant Area
n/a
Annual Production 2,500,000
lb
Production Hrs. Annual 2,040
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $38,333 863,423
kWh
Natural Gas $5,811 2,033
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,705 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,880

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,870 $5,633 $3,870
87,339
kWh
-
02 2.7261: Install timers and/or thermostats $2,320 $1,500 $380
8,499
kWh
$1,940
-
MMBtu
03 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $770 - $770
17,292
kWh
-
04 2.3191: Use demand controller or load shedder $1,185 $2,850 $1,185
-
kWh
-
05 2.7447: Install vinyl strip / high speed / air curtain doors $940 $1,950 $680
15,533
kWh
$260
-
MMBtu
06 2.7492: Use proper thickness of insulation on building envelope $620 $1,620 $450
10,258
kWh
$170
-
MMBtu
TOTAL RECOMMENDED $9,705 $13,553 $7,335
138,921
kWh
$2,370
-
MMBtu
TOTAL IMPLEMENTED $3,880 $5,070 $1,510
34,290
kWh
$2,370
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs