| Assessment Year | 1996 |
|---|---|
| Principal Product | Shrimp, Onionrings, Cheese sticks and french toast |
| NAICS |
n/a
|
| SIC | 2092: Prepared Fresh or Frozen Fish and Seafoods |
| Sales Range | $50 M to 100M |
| # of Employees | 300 |
| Plant Area |
130,000
ft2
|
| Annual Production | 32,000,000
lb
|
| Production Hrs. Annual | 2,340
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $481,564 | 10,296,014 |
kWh
|
$0.047 |
| Electricity Demand | $39,899 | 22,824 |
kW-mo/yr
|
$1.75 |
| Electricity Fees | $9,141 | - |
|
- |
| Natural Gas | $45,239 | 17,732 |
MMBtu
|
$2.55 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $137,342 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $135,230 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $55,998 | $50 |
$51,948
1,105,217
kWh
|
$4,050
-
kW-mo/yr
|
- | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $13,385 | $26,920 |
$12,603
268,171
kWh
|
$782
-
kW-mo/yr
|
- | - | |
| 03 | 2.7261: Install timers and/or thermostats | $3,547 | $450 |
$3,547
75,322
kWh
|
- | - | - | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $988 | $3,270 |
$988
21,102
kWh
|
- | - | - | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $2,622 | $270 |
$2,376
50,410
kWh
|
$246
-
kW-mo/yr
|
- | - | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,004 | $40 |
$1,816
38,687
kWh
|
$188
-
kW-mo/yr
|
- | - | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $1,124 | $520 |
$1,018
21,688
kWh
|
$106
-
kW-mo/yr
|
- | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,057 | $3,503 |
$957
20,516
kWh
|
$100
-
kW-mo/yr
|
- | - | |
| 09 | 3.4115: Recover and reuse cooling water | $49,625 | $65,000 | - | - | - |
$49,625
-
lb
|
|
| 10 | 3.4113: Treat and reuse rinse waters | $2,220 | $975 | - | - |
$2,220
-
Tgal
|
- | |
| 11 | 3.4115: Recover and reuse cooling water | $4,772 | $100 | - | - |
$4,772
-
Tgal
|
- | |
| TOTAL RECOMMENDED | $137,342 | $101,098 |
$75,253
1,601,113
kWh
|
$5,472
-
kW-mo/yr
|
$6,992
-
Tgal
|
$49,625
-
lb
|
||
| TOTAL IMPLEMENTED | $135,230 | $97,308 |
$73,247
1,558,323
kWh
|
$5,366
-
kW-mo/yr
|
$6,992
-
Tgal
|
$49,625
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs