ITAC Assessment: KG0041
ITAC logo
ITAC Assessment: KG0041
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Wheat and White Bread
NAICS
n/a
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $5
M
to 10
M
# of Employees 120
Plant Area 138,000
ft2
Annual Production 27,000,000
pieces
Production Hrs. Annual 5,720
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $87,645 1,319,461
kWh
Natural Gas $50,760 15,829
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,531 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,643

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4133: Use most efficient type of electric motors $6,400 $5,730 $6,400
102,286
kWh
-
02 2.4314: Use synthetic lubricant $1,626 - $1,626
26,084
kWh
-
03 2.7261: Install timers and/or thermostats $458 $300 $458
13,775
kWh
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $407 $188 $407
5,569
kWh
-
05 2.1233: Analyze flue gas for proper air/fuel ratio $378 $1,250 - $378
-
MMBtu
06 2.4221: Install compressor air intakes in coolest locations $262 $260 $262
4,103
kWh
-
TOTAL RECOMMENDED $9,531 $7,728 $9,153
151,817
kWh
$378
-
MMBtu
TOTAL IMPLEMENTED $7,643 $7,468 $7,265
121,630
kWh
$378
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs