Assessment Year | 1994 |
---|---|
Principal Product | Pressure vessels,fractioning columns. |
NAICS |
n/a
|
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $10 M to 50M |
# of Employees | 76 |
Plant Area |
90,000
ft2
|
Annual Production | 200
pieces
|
Production Hrs. Annual | 2,340
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $461,105 | 5,709,848 |
kWh
|
$0.081 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,242 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $6,524 | $2,150 |
$6,524
228,312
kWh
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,688 | $829 |
$1,688
17,585
kWh
|
|
03 | 2.6231: Utilize controls to operate equipment only when needed | $1,618 | $3,000 |
$1,618
56,565
kWh
|
|
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,332 | $15 |
$1,332
46,600
kWh
|
|
05 | 2.7135: Install occupancy sensors | $80 | $130 |
$80
2,931
kWh
|
|
TOTAL RECOMMENDED | $11,242 | $6,124 |
$11,242
351,993
kWh
|
||
TOTAL IMPLEMENTED | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs